Update 26 Aug 2021: Cambridge News reports that these works have been postponed until further notice.
The works start on 1st September and are set to continue for 3 months. They are intended to improve Cottenham's poor drainage and prevent future flooding. There will be considerable disruption for people who come through Cottenham to access Cambridge or who have pupils of the Village College.
Cottenham Parish Council have set up a meeting with Anglian Water next Wednesday to raise concerns so if there are any matters you would like to discuss please forward any comments to my colleague Beth –
-- Jo Brook, Cottenham Parish Council
The original message from Anglian WaterÂ
From: Public.Affairs <
Sent: 18 August 2021 10:33
To: Jo Brook <
Cc: Public.Affairs <
Subject: FW: Anglian Water works in Cottenham
Dear Jo, I am pleased to confirm the start date of our works in Cottenham on the 1st September. These works will take around 3 months and will be to reline 333m of sewers at a value of £200k. Thank you for your continued support with our works in Cottenham and thank you in advance for your patience as we work in the village. I can confirm that we will be writing to customers in Cottenham next week to share an update on these works and I have notified Cllrs Gough and Wilson.
You will know that following extensive CCTV surveys of the village and of the wider catchment, we are working to improve the structural condition of the sewer network. Our work will also help to reduce surface water and groundwater infiltration into specific areas of the foul-only sewer system. This means that during periods of heavy rainfall, the sewer system will be protected and this will reduce the risk of customers losing use of their facilities. Whilst there will be some small excavation works required to access the sewers, the majority of the works will be undertaken using no-dig methods of rehabilitation. We will do this by installing a structural liner between manholes which will minimise disruption and will lower our carbon footprint.
I have outlined the full proposal of works, including road closures below:
The works will be done in 2 phases; with phase 1 covering the High Street and phase 2 covering Rampton Road.
Phase 1 Part 1 - 01/09/21 - 21/09/21
Cottenham High Street between Rooks Street and Broad Lane with a full road closure of this part of the High Street.
Access to the High Street for traffic from Rooks Street will be stopped.
Access to Broad Lane will be controlled via 2-way lights
Phase 1 Part 2 - 22/09/21 - 11/10/21
Cottenham High Street between Lambs Lane and Margett Street with a full road closure of this part of the High Street.
Access to the High Street for traffic from Margett Street will be stopped.
This area of work will also affect the Fire station (opposite Margett Street junction) as they will only be able to turn left onto the High Street.
Phase 1 Part 3 - 12/10/21 - 22/10/21
Cottenham High Street between Lambs Lane and Curringtons Close with a full road closure of this part of the High Street.
Access to the High Street for traffic from Lambs Lane will be stopped.
Access to the Cottenham Tyre and Autocentre will be maintained from the South.
Phase 2 Part 1 - 25/10/21 - 12/11/21
Cottenham Rampton Road; Oakington junction with Rampton Rd will have 2 way lights.
The road will be closed at the junction of Rampton Road to Ellis Close junction.
Phase 2 Part 2 - 15/11/21 - 23/11/21
Cottenham Rampton Road; closure of Rampton Road at The Green with 2 way lights on Histon Road.
Please let me know if you or the Council have any immediate questions.
Kind regards,
Rose Shisler
Stakeholder Engagement Programme Lead
Telephone: 07976 819852
Anglian Water Services Limited
Lancaster House, Lancaster Way, Ermine Business Park, Huntingdon, Cambridgeshire, PE29 6XU